Drone photo of the MCJ construction site from Wednesday, 08.11.2023

Microverse center news: The construction work is progressing rapidly

In autum 2022, development work began on the site for the new microverse building in Rosalind Franklin Street, which is scheduled to be ready for occupancy at the end of 2024.
Drone photo of the MCJ construction site from Wednesday, 08.11.2023
Image: IHB Fritsche
  • Light
  • Liberty
  • Events

Published: | By: Sybille Huck

Picture gallery

  • panorama_20230417
    Image: Bas Dutilh
  • panorama_20230707
    Image: Bas Dutilh
  • panorama_20230718
    Image: Bas Dutilh
  • panorama_20230720
    Image: Bas Dutilh
  • panorama_20230921
    Image: Bas Dutilh
  • panorama_20231006
    Image: Bas Dutilh
  • panorama_20231020
    Image: Bas Dutilh
  • panorama_20231026
    Image: Bas Dutilh
  • panorama_20231127
    Image: Bas Dutilh
  • panorama_20240109
    Image: Bas Dutilh
  • panorama_20240125
    Image: Bas Dutilh

Construction Diary

Drone photo of the MCJ construction site from Wednesday, 08.11.2023

Image: IHB Fritsche

November 2023

 

The building grows

Image: Sybille Huck

October 2023

● Continuation of the formwork and reinforcement work on the ceiling
above level 0
● Concreting of ceiling above level 0 in construction sections 1 & 2

September 2023

● Continuation of the construction of the load-bearing exterior and interior walls
interior walls
● Start of the ceiling formwork
● Safety inspection of the construction site by the BauBG, only
minor complaints

August 2023

● Completion of the floor slab
● Start of the concrete walls & columns on level 0
● Installation of lightning protection
● Start of masonry work for the load-bearing interior walls

Concreting of the 1st construction phase of the floor slab

Image: Bas E. Dutilh

July 2023

● Installation of the foundation earth electrode
● Formwork for the floor slab
● Start installing the reinforcement from west to east
● Concreting of the 1st construction phase of the floor slab

Completion of the excavation and shoring work

Image: Bas E. Dutilh

June 2023

● Completion of the excavation pit and shoring work
● Creation of the installation area for the 2nd part of the construction containers
● Erection of the two construction cranes
● Start of the cleanliness layer and the insulation under the floor slab

Shoring is completed

Image: Sybille Huck

May 2023

● Shoring is completed
● Excavation of the foundation pit
● Installation of the foundation pad

April 2023

● Start shoring on the east and west sides of the construction site
● Further dismantling of the drilling levels
● Application of shotcrete to the bored piles
● Production of the lower horizontal anchors

Completion of the vertical shoring on the north side

Image: Sybille Huck

March 2023

● Completion of the vertical shoring on the north side
● Start of shoring on the south side of the construction site
● Load test of the upper horizontal anchor layer
● Removal of the drilling levels in preparation for the lower horizontal anchors

February 2023

● Continuation of work on the north shoring
● Delivery and installation of a second drilling rig to accelerate speed up the drilling work
● Production of the upper horizontal anchors
● Production of the bored piles for the crane foundations

Construction site in January, 2023

Image: Sybille Huck (VEO group)

January 2023

● Production of the concrete piles on the north side of the construction site
● Insertion of the steel girders for the "Berlin shoring"

December 2022

● Forming the drilling planes
● Production of the drilling templates
● Delivery and assembly of the first drilling rig
● Start of the bored piles on the north side of the construction site

November 2022

● Setting up the construction site
● Setting up the 1st part of the construction container system
● Erection of the construction fence
● Removal of the topsoil
● Start of the creation of the drilling levels

February 2022

● Preparatory work
● Site clearance
● Removal of bushes & shrubs