Published: | By: Sybille Huck
October 2023
● Continuation of the formwork and reinforcement work on the ceiling
above level 0
● Concreting of ceiling above level 0 in construction sections 1 & 2
September 2023
● Continuation of the construction of the load-bearing exterior and interior walls
interior walls
● Start of the ceiling formwork
● Safety inspection of the construction site by the BauBG, only
minor complaints
August 2023
● Completion of the floor slab
● Start of the concrete walls & columns on level 0
● Installation of lightning protection
● Start of masonry work for the load-bearing interior walls
July 2023
● Installation of the foundation earth electrode
● Formwork for the floor slab
● Start installing the reinforcement from west to east
● Concreting of the 1st construction phase of the floor slab
June 2023
● Completion of the excavation pit and shoring work
● Creation of the installation area for the 2nd part of the construction containers
● Erection of the two construction cranes
● Start of the cleanliness layer and the insulation under the floor slab
May 2023
● Shoring is completed
● Excavation of the foundation pit
● Installation of the foundation pad
April 2023
● Start shoring on the east and west sides of the construction site
● Further dismantling of the drilling levels
● Application of shotcrete to the bored piles
● Production of the lower horizontal anchors
March 2023
● Completion of the vertical shoring on the north side
● Start of shoring on the south side of the construction site
● Load test of the upper horizontal anchor layer
● Removal of the drilling levels in preparation for the lower horizontal anchors
February 2023
● Continuation of work on the north shoring
● Delivery and installation of a second drilling rig to accelerate speed up the drilling work
● Production of the upper horizontal anchors
● Production of the bored piles for the crane foundations
January 2023
● Production of the concrete piles on the north side of the construction site
● Insertion of the steel girders for the "Berlin shoring"
December 2022
● Forming the drilling planes
● Production of the drilling templates
● Delivery and assembly of the first drilling rig
● Start of the bored piles on the north side of the construction site
November 2022
● Setting up the construction site
● Setting up the 1st part of the construction container system
● Erection of the construction fence
● Removal of the topsoil
● Start of the creation of the drilling levels
February 2022
● Preparatory work
● Site clearance
● Removal of bushes & shrubs