Microverse center news: The construction work is progressing rapidly
In autum 2022, development work began on the site for the new microverse building in Rosalind Franklin Street, which is scheduled to be ready for occupancy at the end of 2024.
Drone photo of the MCJ construction site from Wednesday, 08.11.2023
Image: IHB Fritsche
- Light
- Liberty
- Events
Published: | By: Sybille Huck
Picture gallery
Construction Diary
September 2023
● Continuation of the construction of the load-bearing exterior and interior walls
interior walls
● Start of the ceiling formwork
● Safety inspection of the construction site by the BauBG, only
minor complaints
August 2023
● Completion of the floor slab
● Start of the concrete walls & columns on level 0
● Installation of lightning protection
● Start of masonry work for the load-bearing interior walls
Completion of the excavation and shoring work
Image: Bas E. DutilhJune 2023
● Completion of the excavation pit and shoring work
● Creation of the installation area for the 2nd part of the construction containers
● Erection of the two construction cranes
● Start of the cleanliness layer and the insulation under the floor slab
April 2023
● Start shoring on the east and west sides of the construction site
● Further dismantling of the drilling levels
● Application of shotcrete to the bored piles
● Production of the lower horizontal anchors
Completion of the vertical shoring on the north side
Image: Sybille HuckMarch 2023
● Completion of the vertical shoring on the north side
● Start of shoring on the south side of the construction site
● Load test of the upper horizontal anchor layer
● Removal of the drilling levels in preparation for the lower horizontal anchors
February 2023
● Continuation of work on the north shoring
● Delivery and installation of a second drilling rig to accelerate speed up the drilling work
● Production of the upper horizontal anchors
● Production of the bored piles for the crane foundations
December 2022
● Forming the drilling planes
● Production of the drilling templates
● Delivery and assembly of the first drilling rig
● Start of the bored piles on the north side of the construction site
November 2022
● Setting up the construction site
● Setting up the 1st part of the construction container system
● Erection of the construction fence
● Removal of the topsoil
● Start of the creation of the drilling levels
February 2022
● Preparatory work
● Site clearance
● Removal of bushes & shrubs